February in facts
- Mole ploughing is complete on Crook main routes 1,3,4 and 6
- Only Crook main routes 2 + splays and 5 left to plough
- 116 properties are live and enjoying B4RN's hyper-fast gigabit service
- Frank and David have blown fibre to 73 houses in the last 3 weeks
- Our dig and fit volunteer team continue to work every Tuesday & Friday focusing on getting Crook route 2 properties ready for connection
- There are another 30 houses ready for routers
John and Jo fitting the CCE box to Fellside Cottage |
Boyd and Jerry admiring a tidy job by digging team |
Frank and David blowing fibre from chamber to 9 properties at Boningate, Crook Route 2 |
Tuesday March 7th, dig team working hard at Fellside house in fine spring weather |